Refurbishment and construction of 4 dams. Earthmoving in excess of 10,000M2 of silt and salt to make good the 4 dams on the mine site. Completed in time and on budget with contract extensions offered after the initial project completion.
Project Timeline:
- 2016 – Exploration drill prep/rehab (ongoing)
- May 2018 – Evaporation Ponds (Dam) re-construction (completed Sept 2018)
- Ongoing – Ad Hoc Earthworks contract
Size of the project:
- In excess of 10,000m2 of earthworks across 4 dam sites
- 10 contractors on site
- 10+ Plant equipment supplied